Prep
Bee
Pakistan
Pakistan's #1 Free MCQ Practice Platform for Govt Job Exams
MCQs
Categories
Quiz
Past Papers
Quiz Mode
Login
Register
Preparing your study page...
Search MCQs
Search and filters
Search
Subject
Any subject
Agriculture
Biology
Chemical Engineering
Chemistry
Computer Science
Current Affairs
Economics
English
Everyday Science
General Knowledge
Intelligence
International Current Affairs
Islamic Studies
Judiciary And Law
Management Sciences
Mathematics
Mechanical Engineering
Medical Science
Pakistan Current Affairs
Pakistan Studies
Pedagogy
Physical Education
Physics
Psychology
Sociology
Software Engineering
Urdu
Difficulty
Any
Easy
Medium
Hard
Language
Any
English
Urdu
Bilingual
Sort
Latest
Oldest
Most attempted
Apply
MEDIUM
ENGLISH
Software Engineering
Which of the following is a people-intensive activity ?
A
Problem solving
Option A
B
Organization
Option B
C
Motivation
Option C
D
Project management
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Who delivers the technical skills that are necessary to engineer a product or an application ?
A
Practitioners
Option A
B
Project managers
Option B
C
Senior managers
Option C
D
None of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following is not a project manager’s activity ?
A
project control
Option A
B
project management
Option B
C
project planning
Option C
D
project design
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Commitments to unrealistic time and resource estimates may result in____________________?
A
project delay
Option A
B
poor quality work
Option B
C
project failure
Option C
D
all of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following is a collection of project coordination technique ?
A
Formal approaches
Option A
B
Formal, interpersonal procedures
Option B
C
Informal, interpersonal procedures
Option C
D
All of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following is the reason that software is delivered late ?
A
Changing customer requirements that are not reflected in schedule changes
Option A
B
Technical difficulties that could not have been foreseen in advance
Option B
C
Human difficulties that could not have been foreseen in advance
Option C
D
All of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following is not a sign that indicates that an information systems project is in jeopardy?
A
Software people don’t understand their customers needs
Option A
B
Changes are managed poorly
Option B
C
Sponsorship is gained
Option C
D
Users are resistant
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Who defines the business issues that often have significant influence on the project ?
A
Practitioners
Option A
B
Project managers
Option B
C
Senior managers
Option C
D
None of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
PM-CMM stands for___________________?
A
people management capability maturity model
Option A
B
process management capability maturity model
Option B
C
product management capability maturity model
Option C
D
project management capability maturity model
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
v Programming language experience is a part of which factor of COCOMO cost drivers ?
A
Personnel Factor
Option A
B
Product Factor
Option B
C
Platform Factor
Option C
D
Project Factor
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition ?
A
External inputs
Option A
B
External outputs
Option B
C
External process
Option C
D
External inquiries
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Who suggested the four different approaches to the sizing problem ?
A
Putnam
Option A
B
Myers
Option B
C
Boehm
Option C
D
Putnam and Myers
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
A make-buy decision is based on whether________________?
A
The software may be purchased off-the-shelf
Option A
B
“Full-experience” or “Partial-experience” software components should be used
Option B
C
Customer-built software should be developed
Option C
D
All of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following term is best defined by the statement: “Derive traceability information to maximize information hiding in the design.” ?
A
Underestimated development time
Option A
B
Organizational restructuring
Option B
C
Requirements changes
Option C
D
None of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following risks are derived from the organizational environment where the software is being developed ?
A
People risks
Option A
B
Technology risks
Option B
C
Estimation risks
Option C
D
Organizational risks
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.” ?
A
Technology change
Option A
B
Product competition
Option B
C
Requirements change
Option C
D
None of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Risk management is one of the most important jobs for a__________________?
A
Client
Option A
B
Investor
Option B
C
Production team
Option C
D
Project manager
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
A
Risk monitoring
Option A
B
Risk planning
Option B
C
Risk analysis
Option C
D
Risk identification
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which activity sits at the core of software requirements analysis ?
A
Problem decomposition
Option A
B
Partitioning
Option B
C
Problem elaboration
Option C
D
All of the mentioned
Option D
Show Answer
Open Detail
MEDIUM
ENGLISH
Software Engineering
Which of the following term is best defined by the statement “The creation of a new codeline from a version in an existing codeline” ?
A
Branching
Option A
B
Merging
Option B
C
Codeline
Option C
D
Mainline
Option D