A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in_______days.
5 5⁄11
Correct answer
B
4 5⁄11
Option B
C
6 4⁄11
Option C
D
6 5⁄11
Option D
Correct answer: A
Explanation
No explanation provided for this MCQ yet.