X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
A
6 days
Option A
10 days
Correct answer
C
15 days
Option C
D
20 days
Option D
Correct answer: B
Explanation
No explanation provided for this MCQ yet.
Hide Answer
Hide Explanation