A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
A
4(2/3) days
Option A
B
4 days
Option B
5(1/3) days
Correct answer
D
1(1/3) days
Option D
Correct answer: C