Mechanical Engineering
Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A
latest start time of succeeding event -earliest finish time of preceding event activity time
Option A
B
latest start time of the event – earliest start time of the event
Option B
C
latest finish time of event – earliest finish time of the event
Option C
anyone of the above
Correct answer
Correct answer: D
Explanation
No explanation provided for this MCQ yet.