If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?
A
latest start time – earliest start time
Option A
B
latest finish time – earliest finish time (EFT)
Option B
C
TL-EFT
Option C
all of the above
Correct answer
Correct answer: D