An optimum project schedule implies_______________?
A
optimum utilization of men, machines and materials
Option A
lowest possible cost and shortest possible time for project
Correct answer
C
timely execution of project
Option C
D
to produce best results under given constraints
Option D
Correct answer: B
Explanation
No explanation provided for this MCQ yet.